Capital Construction Projects

Palo Verde Ave between Carson St and Parkcrest St.

Cast Iron Main Replacement
Project Images      |       Project Map
Status
Paving complete.

Project Description
The project consists of constructing a 12-inch inter-tie between the City of Lakewood and LBWD water systems to transfer water between the two agencies during dry years or in an emergency. The project is located at the southwest corner of the intersection of Palo Verde Avenue and Carson Street in Heartwell Park.

Project Benefits
This project will enhance water quality and improve fire flow protection to the area.
 

Estimated Construction Period
September 2007 - May 2008

Council District(s)
5th

Last Update
May 2, 2008

 


Project Map

For more information on this project, please call Ana Ananda at
(562) 570-2326. For comments on this or any CCP projects, please e-mail us at CIP_comments@lbwater.org.

 
 